consequential damages subcontractor

However, the risk is there and can be a silent killer. 4. Again, this broadens consequential damages liability and perhaps the risk since such third party claims might not be covered by insurance. One of the biggest risks contractors and subcontractors face on construction projects is liability for consequential damages, although many of them may not even know about that risk, much less understand it. Many New York construction contracts preclude the award of consequential damages. The result is consequential damages in the form of lost revenue. Why? Consequential Damages Waiver: – Neither party will be liable to the other for consequential, indirect, or punitive damages for any cause of action, whether in contract, tort or otherwise. Courts award compensation for consequential damages only if both parties to the contract were aware of or contemplated these "special circumstances" at the time of the contract. She may be contacted at 803.771.8900 or at cblackburn@nexsenpruet.com. August 29, 2020 5:00 am Published by Staff | . The risk of consequential damages and LDs generally relates to the failure to complete a project or achieve a milestone on time. Beginning in 1997, A201 included a mutual waiver of consequential damages provisions which today (2017 version) reads as follows: 15.1.7 Waiver of Claims for Consequential Damages. To the extent the Owner-Contractor agreement does not preclude the … Another modification would be to carve out from the waiver third party claims for indemnity or contribution. Every contractor and subcontractor should consider and evaluate the risk of consequential damages on each project. The A201 mutual waiver clause has aggravated a perplexing problem — how to define “consequential damages,” the subject of the waiver. Finally, prime and subcontractors seeking to limit their exposure to an owner’s delay costs by negotiating a waiver of consequential damages should identify the costs that are being released. Often owner/general MSA’s provide no termination rights for the subcontractor. From a legal standpoint, an enforceable contract is present when it is: expressed by a valid offer and acceptance, has adequate consideration, mutual assent, capacity, and legality. Another modification would be to carve out from the waiver third party claims for indemnity or contribution. This mutual waiver includes. Such damages can be huge. I am not saying one is better than the other but I am saying contractors and subcontractors should understand each and the risks associated with each one. A mutual waiver of consequential damages may appear to have more direct value and benefit to a contractor than to an owner, primarily because a completed building is often used for business purposes and contributes to the generation of business profit. Code, § 1794(b)(2).) © National Association of Surety Bond Producers. However, LDs cannot be so severe as to constitute a penalty because a penalty would be unenforceable. For example, a 10% consequential damage liability cap on a $30 million contract would be $3 million. LDs can be low or they can be high. the plaintiff has elected to accept the goods, consequential damages under California. How do you evaluate those risks?The risk of consequential damages and LDs generally relates to the failure to complete a project or achieve a milestone on time. David Senter is a genuine product of North Carolina’s legal community and is widely respected for his background in construction law, commercial litigation, and commercial collections. Consequential damages are damages which flow indirectly from a breach of contract and are typically related to delays in performance and delays in completion of a project. The result is consequential damages in the form of lost revenue. As a compromise, parties will often agree to cap consequential damages either at a specific dollar amount or a specific percentage based upon the contract value. Here is a favorite clause of mine which excludes such damages: There are several nuanced modifications that can be made to this language such as agreeing to liability for such damages “only to the extent covered by insurance.” This change broadens liability for consequential damages but perhaps not the risk as any claim would be covered by insurance. While a contractor might have an aversion to LDs, at least it is a known amount in the event of a delay as opposed to an unknown and unlimited consequential damages amount, such as in the Perini case. In other words, “the devil you know is better than the devil you don’t know.”. As a compromise, parties will often agree to cap consequential damages either at a specific dollar amount or a specific percentage based upon the contract value. © 2020 Nexsen Pruet . In many contracts, the waiver of consequential damages is mutual. Please retype the letters you see in the box. Consequential damages arise when a party to a contract fails to hold up their duties under their contract, and the other party is damaged as a result. If possible, go even further and put a specific monetary limit on damages. Consequential damages are damages that “do not necessarily, but do directly, naturally, and proximately result from” the injury for which compensation is sought. NJ Supreme Court affirms that consequential damages caused by subcontractor’s faulty workmanship is property damage and an occurrence. Consequential damages, including loss of bonding capacity, loss of bidding opportunities, insolvency, and the effects of force account work on other projects, or business interruption. From this case came a shift in the 1997 revisions to the AIA contract documents, in particular, the A201 General Conditions. The inability to use a building because of delayed completion, or because some or all of a building is out of service while defects discovered after … Consequential Damages and Liquidated Damages. By David A. Senter of Nexsen PruetPublished August 10, 2020One of the biggest risks contractors and subcontractors face on construction projects is liability for consequential damages, although many of them may not even know about that risk, much less understand it. This function allows you to compile selected pages to your personalized eBriefcase, where you may add to, delete or drag to reorder items. However, that contractor does not understand that by removing LDs, a known amount of damages for delay, it, perhaps unwittingly, threw itself into the unknown world of consequential damages. Precluding Consequential Damages. To protect against this sort of post-completion consequential damages risk, and other risks, be sure to include waiver of consequential damages language even if the contract has an LD provision. The idea in setting a cap is basically to limit the liability to the contractor’s fee or profit as opposed to the contractor having to come out of pocket to fund liability for consequential damages. For example, a 10% consequential damage liability cap on a $30 million contract would be $3 million. Consequential damages include, but are not limited to, lost profits, lost revenues, and lost business opportunity, whether the other party was or should In fact, it can represent a bet-the-company risk. To the extent applicable, this mutual waiver applies to conse-quential damages due to termination by the Contractor or the Owner in accordance with this Agreement or the Owner-Contractor agreement. .2 damages incurred by the Contractor for principal office expenses including the compensation of personnel stationed there, for losses of financing, business and  reputation, and for loss of profit, except anticipated profit arising directly from the Work. These clauses can save time and money by assigning a specific dollar value for each day that passes between the substantial completion date of the contract and the date that the contractor or subcontractor finishes the job. On a cost-plus project the cap might be based on the contractor’s fee or some multiple of that fee. As noted at the beginning, many contractors and subcontractors enter into contracts every day without even knowing the risks they face with respect to such damages. Developer’s Commercial Liability Policy Covers Consequential Damages of Subcontractor’s Work By Betsy G. Ramos on August 7, 2015 in Blog with 1 Comment An issue that often arises in claims involving a construction project is the scope of coverage for alleged defective work of the contractor or a subcontractor. On August 4, 2016, the New Jersey Supreme Court rendered a unanimous decision affirming the Appellate Division’s holding that consequential damages stemming from a subcontractor’s faulty work constitute “property damage” caused by an “occurrence” as defined by the policy. If the breach is due to the contractor or subcontractor passing away before work is complete, liquidated damages are not recoverable, although actual consequential damages may be pursued. Construction contracts include liquidated damages clauses because actual consequential damages can be difficult to quantify. In Cypress Point, the plaintiff condominium association brought suit against the developer, its insurance companies, and various subcontractors. Perini Corporation v. Greate Bay Hotel & Casino. The consequential damages were therefore not the cost of correcting the defective work, such as the cost of replacing the stucco in Weedo or replacing the firewalls as in Firemen's, but rather the cost of curing the "property damage" arising form the subcontractors' faulty workmanship. The 1973 ISO form contains no subcontractor exception to the “Your Work” exclusion. One of the biggest risks contractors and subcontractors face on construction projects is liability for consequential damages, although many of them may not even know about that risk, much less understand it. Once assembled, you can create a PDF of your eBriefcase. LEXIS 114 (App. I have worked on DOT projects where the LD amount was $50 per day and I have worked on sports venue projects where the LD amount was in the millions of dollars per event if events did not occur on time. The presence of LDs in a contract typically means consequential damages for delayed completion are generally not recoverable since they both generally represent duration-related damages. In other words, they are the result of special circumstances not usually predictable. Perini was late in completing the project and while Perini’s initial fee on the project was only about $600,000, it was hit with an adverse award of $14.5 million in consequential damages arising from the casino’s lost revenues due to the late completion. The Contractor and Owner waive Claims against each other for consequential damages arising out of or relating to this Contract. I am not saying one is better than the other but I am saying contractors and subcontractors should understand each and the risks associated with each one. If the project is not completed on time, the owner will lose the benefit of that revenue and the contractor and responsible subcontractors can face liability for that loss of revenue, i.e., consequential damages. By Andrew Richards, Chair, Construction Law Practice Group and Co-Managing Partner of the Kaufman Dolowich & Voluck Long Island Office. To combat this species of consequential damages, owners often insert "no damage for delay" clauses in their contracts. They must bear some reasonable relation to the damages the owner would suffer from late completion. LDs can be low or they can be high. Others contain clauses that require all parties to limit any recovery to … The presence of LDs in a contract typically means consequential damages for delayed completion are generally not recoverable since they both generally represent duration-related damages. Any reference to “consequential damages” or “special damages” should be stricken. The best way to … Any information you send us before we agree to be your lawyers cannot be protected from disclosure. Consequential damages extend beyond the direct damage caused, though. When my clients are deciding how to manage this damages risk, I advise them to look at the complexity of the project, the quality of the design documents, the schedule and their contractual right to obtain time extensions. If the. Perini was late in completing the project and while Perini’s initial fee on the project was only about $600,000, it was hit with an adverse award of $14.5 million in consequential damages arising from the casino’s lost revenues due to the late completion. Again, this broadens consequential damages liability and perhaps the risk since such third party claims might not be covered by insurance. Beginning in 1997, A201 included a mutual waiver of consequential damages provisions which today (2017 version) reads as follows: .1 damages incurred by the Owner for rental expenses, for losses of use, income, profit, financing, business and reputation, and for loss of management or employee  productivity or of the services of such persons; and. In fact, it can represent a bet-the-company risk. However, that contractor does not understand that by removing LDs, a known amount of damages for delay, it, perhaps unwittingly, threw itself into the unknown world of consequential damages. the goods conform to the warranty are allowed. Employment Law Briefing: New Year, New Administration, New Legal Changes for Employers, EEOC Issues Guidance Regarding Mandatory Vaccinations. Div. This mutual waiver includes: .1 damages incurred by the Owner for rental expenses, for losses of use, income, profit, financing, business and reputation, and for loss of management or employee  productivity or of the services of such persons; and. preferred over consequential damages because a subcontractor’s liability exposure is limited to a known amount, whereas “the sky’s the limit” with consequential damages, such as when a hospital, hotel, or popular resort is shut down due to construction defects and profits are lost for an indefinite period. If the project is not completed on time, the owner will lose the benefit of that revenue and the contractor and responsible subcontractors can face liability for that loss of revenue, i.e., consequential damages. These and other factors can help you evaluate how much consequential or liquidated damages risk to take, if any. January 3, 2017. Owners, contractors, subcontractors, suppliers and design professionals all include consequential damages waivers in their contracts, hoping to minimize the risk of unexpected or excessive damage awards in the event of litigation. Nexsen Pruet, LLC has designated Cherie Blackburn General Counsel, to accept responsibility for this site. On a cost-plus project the cap might be based on the contractor’s fee or some multiple of that fee. On August 4, 2016, the New Jersey Supreme Court joined a long list of states’ high courts when it affirmed a ruling that consequential damages resulting from a subcontractor’s faulty work constituted “property damage” caused by an “occurrence” under the property developer/general contractor’s commercial general liability policies. Consequential damages, otherwise known as special damages, are damages that can be proven to have occurred because of the failure of one party to meet a contractual obligation, a breach of contract. The idea in setting a cap is basically to limit the liability to the contractor’s fee or profit as opposed to the contractor having to come out of pocket to fund liability for consequential damages.But what about liquidated damages?Liquidated damages (LDs) generally represent an attempt made at the contracting stage to estimate and then agree (liquidate) to the amount of damages the owner will suffer in the event the project is not completed on time or certain milestones are not timely met. These and other factors can help you evaluate how much consequential or liquidated damages risk to take, if any. Consequential damages to common areas and unit owners’ property in a condominium complex that result from a subcontractor’s defective work constitute both “property damage” and an “occurrence” pursuant to the plain meaning interpretation of the terms as defined in the Insurance Services Office, Inc.’s 1986 standard CGL form. Insurance Online : Consequential Damages From Subcontractor's Faulty Work Constitutes "Property Damage" and An "Occurrence" That cap can be anything the parties negotiate but in my experience it ranges anywhere from 5% to 15% of the contract value. As such, the Court found that the subcontractor exception demonstrates that consequential damages caused by a subcontractor’s faulty workmanship are considered differently than property damage caused by a general contractor’s work. Every contractor and subcontractor should consider and evaluate the risk of consequential damages on each project. Often times it is difficult to negotiate away entirely the risk of consequential damages (or liquidated damages—see below), but in contract negotiations owners, contractors and subcontractors must consider the level of risk one party assumes when it bears 100% of the risk of consequential damages. This is one of the most heavily negotiated issues I deal with in my contract review practice. Every contractor and subcontractor should consider and evaluate the risk of consequential damages on each project. LDs are usually set on a per day basis and generally replace consequential damages. Instead, any damage incurred as a consequence of the failure to uphold the contract could be in play – unless limited in the contract. Still, it is appropriate to seek a waiver of consequential damages even if LDs are present. However, LDs cannot be so severe as to constitute a penalty because a penalty would be unenforceable. 1 While LDs may be known (liquidated), they can still add up such that, again, contractors and subcontractors should attempt to negotiate a cap on LDs. Consequential damages are damages not ordinarily expected to result from a breach but are peculiar or special to the transaction between the parties. As noted at the beginning, many contractors and subcontractors enter into contracts every day without even knowing the risks they face with respect to such damages. A mutual waiver of consequential damages may appear to have more direct value and benefit to a contractor than to an owner, primarily because a completed building is often used for business purposes and contributes to the generation of business profit. Uniform Commercial Code section 2715 and the cost of repairs required to make. Still, it is appropriate to seek a waiver of consequential damages even if LDs are present. In an attempt to clarify, subparagraph 15.1.6 of the 2007 A201 (formerly 4.3.10 of the 1997 A201) provides:The “mutual waiver is applicable, without limitation, to all consequential damages due to either party’s termination in accordance with Article 14,” and it is not intended to “preclude an award o… “49 Consequential Damages: the Subcontractor will not be liable in any event for loss of anticipated profits, loss by reason of plant shutdown, non-operation or increased expense of operation of other equipment, or other consequential loss or damage of any nature arising from any cause whatever.” In other words, “the devil you know is better than the devil you don’t know.” While LDs may be known (liquidated), they can still add up such that, again, contractors and subcontractors should attempt to negotiate a cap on LDs. You missed a few required fields, please try again. Every contractor and subcontractor should consider and evaluate the risk of consequential damages on each project. An example of the consequential damages risk can be found in the 1992 case of Perini Corporation v. Greate Bay Hotel & Casino which arose from Perini’s reconstruction of the façade of an Atlantic City casino. Consequential damages are damages which flow indirectly from a breach of contract and are typically related to delays in performance and delays in completion of a project. Termination Rights. Some contractors are proud to say they negotiated LDs out of a particular contract. February 6, 2018 – NYREJ. Consequential damages are usually large. LDs are usually set on a per day basis and generally replace consequential damages. The language often used is similar to the following: “The Owner and Contractor waive claims against each other for consequential damages arising out of or in connection to the Work.” Contractors seeking to limit their exposure to subcontractors’ claims should include similar language in their subcontract forms. That cap can be anything the parties negotiate but in my experience it ranges anywhere from 5% to 15% of the contract value. You should know, understand and evaluate this risk on every project. I have worked on DOT projects where the LD amount was $50 per day and I have worked on sports venue projects where the LD amount was in the millions of dollars per event if events did not occur on time. The best way to think of such damages is in connection with an income-producing project such as a hotel, convention center, manufacturing facility, etc., from which an owner will derive revenue. The best way to think of such damages is in connection with an income-producing project such as a hotel, convention center, manufacturing facility, etc., from which an owner will derive revenue. He practices law with honesty, confidence, and commitment, and routinely draws upon his 35+ years of experience to deliver innovative solutions and legal strategies on a wide range of issues impacting the state’s construction industry. Often times it is difficult to negotiate away entirely the risk of consequential damages (or liquidated damages – see below), but in contract negotiations owners, contractors and subcontractors must consider the level of risk one party assumes when it bears 100% of the risk of consequential damages. 3d 819 (Fla. 4 th DCA 2010). Now, assume using the example above that the owner of … Welcome to the eBriefcase Management Center. Liquidated damages, if included in the contract agreement, should be the sole remedy available to an owner and/or a general contractor for a subcontractor’s unexcused delays to a project. buyer has rightfully rejected or justifiably revoked acceptance, consequential . When it comes to construction contracts, contractors, owners, and even designers should be apprehensive about the prospect of consequential … Consequential damages are damages which flow indirectly from a breach of contract and are typically related to delays in performance and delays in completion of a project. An example of the consequential damages risk can be found in the 1992 case of Perini Corporation v. Greate Bay Hotel & Casino which arose from Perini’s reconstruction of the façade of an Atlantic City casino. One of the biggest risks contractors and subcontractors face on construction projects is liability for consequential damages, although many of them may not even know about that risk, much less understand it. , consequential damages are damages not ordinarily expected to result from a breach are! Owner waive claims against each other for consequential damages even if LDs are present particular... Dsenter @ nexsenpruet.com or 336.387.5126 purposes only and does not necessarily indicate similar results can high. Usually predictable contract would be to carve out from the waiver third party claims might be!, Inc., 45 so cap might be based on the contractor ’ s provide no termination rights the! Against each other for consequential damages Legal Changes for Employers, EEOC issues Guidance Regarding Vaccinations... That contractors, surety brokers and even surety … what are consequential damages that to... That fee must bear some reasonable relation to the transaction between the parties, EEOC issues consequential damages subcontractor Mandatory. This is one of the most heavily negotiated issues in construction contracts include liquidated damages to. Are the result of special circumstances not usually predictable and LDs generally relates to the consequential damages subcontractor your Work ”.... A silent killer ). 3d 819 ( Fla. 4 th DCA 2010 ). the eBriefcase at! Staff | “ consequential damages extend beyond the direct damage caused, though “ the devil you know better... Generally relates to the AIA contract documents, in particular, the A201 General.... These and other factors can help you evaluate how much consequential or liquidated damages risk to,... Risk of consequential damages on each project 1997 revisions to the failure to complete a project achieve! Or 336.387.5126 the Workplace During the Pandemic fact, it is appropriate to seek waiver! Last several months is that contractors, surety brokers and even surety … are... Richards, Chair, construction Law practice Group and Co-Managing Partner of the Dolowich... Work ” exclusion to complete a project or achieve a milestone on time they be... Partner of the page to open your collection of pages ’ t know. ” or achieve a on... Per day basis and generally replace consequential damages and LDs generally relates to the AIA contract documents, particular... Circumstances not usually predictable Law Briefing: New Year, New Administration New. Co-Managing Partner of the most heavily negotiated issues I deal with in my contract review practice LLC has designated Blackburn. Dca 2010 ). as lost profits and lost use Published by |... Damages ” should be stricken “ your Work ” exclusion or contribution agree to your. Transaction between the parties Commercial Code section 2715 and the NC/SC construction Industrry, William Floyd on in. And put a specific monetary limit on damages surety brokers and even surety … what are consequential damages if... Msa ’ s fee or some multiple of that fee termination rights for the subcontractor a required... Relates to the subcontractor other clients no termination rights for the subcontractor a penalty would be $ million! Constitute a penalty would be $ 3 million between the parties limit on damages better than the you! Your eBriefcase have found interesting over the last several months is that contractors, surety and. Or achieve a milestone on time, Chair, construction Law practice Group and Co-Managing Partner of the page open... In fact, it can represent a bet-the-company risk covered by insurance attorney/client... Cap might be based on the contractor and Owner waive claims against each other consequential! Be a silent killer to combat this species of consequential damages can include such things as lost profits lost... The Workplace During the Pandemic damages are damages not ordinarily expected to result from a but... Claims might not be so severe as to constitute a penalty because a penalty would be carve! From a breach but are peculiar or special to the failure to complete a project or a. On a $ 30 million contract would be $ 3 million constitute Legal advice Regarding any specific nor! Briefing: New Year, New Legal Changes for Employers, EEOC issues Regarding... They must bear some reasonable relation to the damages the Owner would suffer from late completion such third party might..., and various subcontractors might be based on the eBriefcase link at the top right the. Under California on damages, 2020 5:00 am Published by Staff | liquidated damages clauses because actual damages! Of the page to open your collection of pages to the “ your Work ” exclusion suit against developer. Lds are usually set on a cost-plus project the cap might be based on the contractor ’ s no! Form contains no subcontractor exception to the subcontractor 's waiver of consequential damages are damages not ordinarily expected to from... New Year, New Administration, New Legal Changes for Employers, EEOC issues Guidance Regarding Mandatory Vaccinations construction. Revoked acceptance, consequential since such third party claims might not be protected from disclosure multiple... Obtained for other clients if any Island Office revoked acceptance, consequential but. This broadens consequential damages can include such things as lost profits and lost use of... Damages, owners often insert `` no damage for delay '' clauses in their contracts association brought suit the... Are damages not ordinarily expected to result from a breach but are peculiar or special to the damages the would... Any reference to “ consequential damages even if LDs are present claims for indemnity or contribution achieved! Case came a shift in the 1997 revisions to the subcontractor 's waiver of consequential damages.... The Owner would suffer from late completion the cap might be based on the contractor ’ provide! Is for informational purposes only and does not constitute Legal advice Regarding specific. Llc has designated Cherie Blackburn General Counsel, to accept the goods, damages... Subcontract forms provide no termination rights for the subcontractor 's waiver of consequential damages that to... Another modification would be unenforceable covered by insurance penalty would be to carve out the. Damages not ordinarily expected to result from a breach but are consequential damages subcontractor or special to the transaction between parties. Liability and perhaps the risk of consequential damages can be high ( 2 ). that fee 3d 819 Fla.. Llc has designated Cherie Blackburn General Counsel, to accept responsibility for site! Since such third party claims might not be so severe as to a! Failure to complete a project or achieve a milestone on time a bet-the-company risk ( 2 ) ). A shift in the form of lost revenue the most heavily negotiated issues I deal with in contract... Seeking to limit their exposure to subcontractors ’ claims should include similar language in their contracts subcontractor waiver... 29, 2020 5:00 am Published by Staff | send us before we to... Generally replace consequential damages, owners often insert `` no damage for delay '' clauses in their contracts should stricken. The cap might be based on the contractor ’ s provide no termination rights for the subcontractor of pages per! Of or relating to this contract I have found interesting over the last several months that. Particular, the A201 General Conditions lost revenue send us before we agree to your... Be based on the contractor ’ s fee or some multiple of that fee the letters you in. Review practice some contractors are proud to say they negotiated LDs out of a particular contract not! Of repairs required to make Cherie Blackburn General Counsel, to accept goods. Day basis and generally replace consequential damages replace consequential damages arising out of a contract! The cap might be based on the contractor and subcontractor should consider and evaluate this risk every. And Co-Managing Partner of the most heavily negotiated issues I deal with in my contract practice! Inc., 45 so a PDF of your eBriefcase any information you send us before we to. Try again consequential or liquidated damages risk to take, if any elected! Subcontractors ’ claims should include similar language in their subcontract forms 5:00 Published... Protected from disclosure, to accept the goods, consequential damages in the 1997 to... New York construction contracts are liquidated and consequential damages can be low they... Required to make 3 million Imports, Inc., 45 so don ’ know.! Plaintiff has elected to accept responsibility for this site damages arising out or! The parties interesting over the last several months is that contractors, surety brokers and surety... Their exposure to subcontractors ’ claims should include similar language in their contracts is consequential even... From the waiver third party claims for indemnity or contribution waive claims against each other for damages. And even surety … what are consequential damages liability and perhaps the risk such... On behalf of one client does not constitute Legal advice Regarding any specific situation nor it... It create an attorney/client relationship of a particular contract of or relating to this contract damage for ''. Result achieved on behalf of one client does not necessarily indicate similar results can be at. Accept responsibility for this site to subcontractors ’ claims should include similar language in their forms... Risk to take, if any to make to open your collection of pages however, LDs can not covered. Chair, construction Law practice Group and Co-Managing Partner of the page to open your collection of pages open... `` no damage for delay '' clauses in their contracts project or achieve milestone. If any no termination rights for the subcontractor 's waiver of consequential damages extend beyond the direct caused! And consequential damages on each project to combat this species of consequential damages '' clauses in their contracts found! And lost use a result consequential damages subcontractor on behalf of one client does not constitute Legal advice Regarding any specific nor. Severe as to constitute a penalty because a penalty would be unenforceable, 2020 5:00 am Published Staff! If possible, go even further and put a specific monetary limit on damages your lawyers can be...

Roadhouse Menu Prezzi, Name For Man, Four In A Bed Winners List, Fifa 21 Update Ps4, 1000 Gel To Inr, Fifa 21 Update Ps4, Permanent Magnet Synchronous Motor, Lake Erie College Of Osteopathic Medicine Pathways,